Priestley Street, Mittagong - Culvert Upgrade

  • Project typeCulvert Upgrade and Road Pavement Reconstruction
  • Project valueCompleted January 2025
  • Project schedule1st July 2024 until January 2025
  • Contractor nameWEM Civil
  • Completion Date31 January 2025
Priestley St Mittagong 20220706_105622.jpg

Project Works

Works for this project commenced 1 July 2024 and were completed January 2025. The works included:

  • Installation of an Inquik Integral Bridge
  • Pavement reconstruction
  • Standard 1.5m footpath and safety fence installation
  • Bank stabilisations, tree removals and re vegetation 

View image slider of the Priestley Street Culvert Upgrade below. Use the slider to move between the before and after images. 

Background

During the flooding events in February and March 2022, the run-off from Chinaman’s creek caused significant damage to the current storm water pipes, headwalls, and road pavement, at Priestley Street in Mittagong. Subsequently, the road and bank channel have suffered erosion and approximately 20 meters of road pavement needs to be reconstructed. To ensure efficient drainage of the creek water, it was necessary to build a drainage structure. The upgrade of the culvert, and associated works were part of the disaster recovery efforts.

Community Impacts 

Road users and pedestrians were advised to exercise caution in the presence of heavy machinery and construction workers in the area. When travelling through the work zones it is essential to exercise care and adhere to the altered traffic conditions. A section of the road was closed during the construction period and signs for detours were placed around the area, from Monday 1 July 2024. The Traffic Management Plan was approved by Council. The construction works were undertaken ensuring minimal disruption and inconvenience was experienced by road users and neighbouring properties.

Contact details