Throughout December, we continued to deliver improvement works across the road network.  

Pothole Repairs:  

  • 422 potholes were filled and repaired with the vast majority around Braemar, Willow Vale, Renwick, Welby, Hill Top, Robertson, Kangaloon and Glenquarry.  

  • During January, crews will focus on pothole repairs in Bowral and Burradoo. 

Road Upgrades:  

  • 3.75 kilometres of unsealed roads and 7.5 kilometres of associated drainage on River View Road, Yullie Avenue and Rockliegh Road in Bundanoon, and Railway Parade Balmoral, have been upgraded.  

Asphalt and Reseal Program 24/25

24/25 Asphalt Program

 

Albion Street, Mittagong

Completed

Bromhall Road, Bundanoon

Completed

Clarence Street, Moss Vale

Completion programmed by 31 March 2025

IGA carpark

Completion programmed by 31 March 2025

Cowpastures Road, Bowral

Completed

Ellsmore Road, Exeter

Completed

Farnborough Drive, Moss Vale

Completed

Farnham Close, Mittagong

Completed

Hampton Court, Moss Vale

Completed

Harley Street, Bowral

Completion programmed by 31 March 2025

James Street, Moss Vale

Completed

Jensens Lane, Exeter

Completed

Lackey Road, Moss Vale

Completed

Loris Street, Bowral

Completion programmed by 31 March 2025

Martha Street, Bowral

Completion programmed by 31 March 2025

Mona Street, Bowral

Completed

Old Hume Hwy - Mittagong

Completion programmed by 31 March 2025

Pioneer Street, Mittagong

Completion programmed by 31 March 2025

Princes Street, Mittagong

Completion programmed by 31 March 2025

Robina St

Completion programmed by 31 March 2025

St Martins Grove, Bowral

Completion programmed by 31 March 2025

Wembley Road, Moss Vale

Completion programmed by 31 March 202

Wingecarribee Street

Completion programmed by 31 March 2025

Yarrawa Street, Moss Vale

Completed

 

24/25 Reseal Program

 

Stonequarry Creek Road, Werai

Completion programmed by 31 March 2025

Old Hume Hwy, Berrima

Completed

Quarry Road, Bundanoon

Completed

Charlotte Street, Burradoo

Completion programmed by 31 March 2025

Drapers Road, Colo Vale

Completion programmed by 31 March 2025

Pine Street, Colo Vale

Completion programmed by 31 March 2025

Middle Rd, Exeter

Completion programmed by 31 March 2025

Moresby Hill Road, East Kangaloon

Completion programmed by 31 March 2025

Railway Parade, Mittagong

Completion programmed by 31 March 2025

Bulwer Road, Moss Vale

Completed

Wilson Drive, Colo Vale

Completion programmed by 31 March 2025

 


Robinson Street Culvert Renewal Project Complete  

The Robinson Street Culvert Renewal Project in Mittagong is now complete.  The project replaced a drainage crossing that was damaged in a flood in February 2022 with new concrete box culverts. The upgrade will increase the capacity of water that can flow through the creek crossing during a large storm, preventing future flooding events.  

The road surface is wider, with a more durable asphalt sealing surface and a drainage system that leads to improved water quality runoff. New signage and guardrails have also been installed to enhance safety. Environmental improvements have been made to the creek bed and banks through rock lining and grass seeding of exposed areas.  

The project budget $680,000 was jointly funded by Council and Transport for NSW Disaster Recovery Funding Arrangements (DRFA).  

Find out more!

Drone footage of renewed Robinson Street Mittagong Culvert