Road Ahead: Progress on Repairs and Projects - March
Published on 03 April 2025
With favourable weather conditions throughout March, the works crews have been busy delivering improvement works across our road network.
Pothole Repairs:
- 440 potholes were filled and repaired with the vast majority in Belmore Falls, Robertson, Kangaloon, ColoVale and Hill Top. Heavy patching also occurred on Meryla Road and Wombeyan Caves Road.
- 255 customer requests were processed and resolved for the month
- During April, crews will address potholes in Bowral, Mittagong and Moss Vale.
Road Upgrades:
- 8.45 kilometres of unsealed roads were graded on Iona Park Road, Walkers Road, Red Hills Road, Amy Street, Willian Street, Coates Road, Athol Street, Victoria Street, Harry Street, Seabrook Road, and Birchalls Lane. These works included 17 kilometres of associated drainage works.
- 1900m of drainage work was completed along sealed roads in Medway and Kangaloon.
- Resealing Program: Prep Works on 150m of Wilson Drive, which will continue as a focus for April. Stabilisation works was undertaken on Drapers Rd (325m) and resealing works on Pine Street (260m).
- Asphalt renewal: Prep Works on 100m of Wembley Rd were undertaken.
New Playspace at David Woods Oval
Excitement is building as construction on the playspace in East Bowral, located at David Wood Playing Fields, progresses. The highlight of the playground is the newly completed pump track, which has been carefully turfed and is currently awaiting line marking.
The majority of the concreting works will be finalised this week, including a learn to ride area for children. Landscaping has also begun, with over 2,000 plants set to be incorporated into the space, enhancing the natural beauty of the area. Over the coming weeks, new all accessible play equipment will be installed thanks to the generous support from The 4k. Following the arrival play equipment and picnic shelters, rubber softfall will be installed and mulching undertaken for a safe and enjoyable environment.
The playspace remains on track to be opened in late June, subject to weather.